Eglinton Crosstown LRT · Toronto, Ontario
For most of 2017 the owner's own advisors reported the Eglinton Crosstown falling behind, while the builder kept certifying it would finish on schedule. Ontario's Auditor General later examined what the owner asked for before it paid to protect the date.
Figures in CAD. Every number on this page links to its source below.
The gap
Months from contract signing to opening
The record
Pick any event. Where a control point would have sat, you'll see what ProgramWarden puts in front of a named person at that moment.
The agency's technical advisors report the consortium falling behind, and the agency itself notes roughly 13 weeks of slippage. Through December 2017 the consortium continues to certify that it will finish on time. The Auditor General found the contract left the owner limited remedies for as long as that certification was given.
Control point · Evidence gates
A status of "on track" sits beside a readiness figure computed from evidence. When the two disagree, the gate shows the gap in the open: claimed ready, required items missing.
How the product behaves at a moment like this one. Not a claim about what would have happened on this project.
What the record shows
On the record
On-time certifications continued through 2017 while the owner's advisors reported the schedule slipping by about 13 weeks.
In ProgramWarden · Evidence gates
Readiness is a number computed from required evidence. Nobody types it in, and a team that marks a gate ready with items missing is shown as exactly that.
On the record
The Auditor General reported that documentation supporting the settlement amount was not requested before it was paid.
In ProgramWarden · Evidence gates
Go is refused while required evidence is missing. Conditional approvals must state their conditions. Every decision is logged with approver, basis and conditions, and cannot be edited afterwards.
On the record
Advisors' design warnings in 2017 preceded years of open quality issues.
In ProgramWarden · Named escalation
Review comments and actions carry an owner and a date. Past due, they escalate on a fixed schedule to named people, and a level-three escalation blocks the gate it belongs to.
None of it needed a megaproject. The same three things happen on a $20 million station upgrade, with fewer people watching.
Independent analysis of public records. ProgramWarden was not used on this project and has no relationship with, or endorsement from, any organization named. Statements about what a control "would have" shown are illustrations of how the product works, not claims about what would have happened.
Set up one program, one gate and its evidence in an afternoon. Fourteen days of the full product, no card.
The walkthrough is with the founder, an owner-side program manager. No sales deck.