Ottawa Confederation Line, Stage 1 · Ottawa, Ontario
A public inquiry led by a judge examined how Ottawa's light rail line was accepted and opened in 2019. Its findings read like a catalogue of what happens when completion criteria are negotiable and the results travel by private message.
Figures in CAD. Every number on this page links to its source below.
The gap
Days that had to meet the dependability standard
Shorter bar = an easier standard to meet.
Double-car trains required to be available
Shorter bar = an easier standard to meet.
The record
Pick any event. Where a control point would have sat, you'll see what ProgramWarden puts in front of a named person at that moment.
The contracted date passes. Several replacement dates follow and are also missed. The inquiry found that readiness dates given to the city were inaccurate, and that the city repeated them publicly.
Source:Report of the Ottawa Light Rail Transit Public Inquiry
Control point · Evidence gates
A gate whose target date passes without a decision is listed as late, with days and reason, on the first screen an executive sees. A new date does not clear the old one from the record.
How the product behaves at a moment like this one. Not a claim about what would have happened on this project.
What the record shows
On the record
The inquiry found the trial-running standard was lowered because the system could not meet the one previously agreed, and that passes and fails were negotiated between the parties.
In ProgramWarden · Evidence gates
A gate's evidence checklist and weights are editable, and each edit is an audit event with before and after values, visible to the directors accountable for the gate.
On the record
The inquiry found complete test results and the change in standard did not reach elected council before the line was accepted.
In ProgramWarden · Named escalation
Readiness, missing evidence and open escalations are on the gate itself and in the weekly digest. There is one version, and it is the computed one.
On the record
The inquiry found substantial completion was agreed with known deficiencies carried into service.
In ProgramWarden · Evidence gates
Go is refused while required evidence is missing. The only way through is a conditional decision that names its conditions, and a level-three escalation blocks the gate outright.
None of it needed a megaproject. The same three things happen on a $20 million station upgrade, with fewer people watching.
Independent analysis of public records. ProgramWarden was not used on this project and has no relationship with, or endorsement from, any organization named. Statements about what a control "would have" shown are illustrations of how the product works, not claims about what would have happened.