Honolulu Rail (Skyline) · Honolulu, Hawaiʻi
Honolulu's elevated rail line runs beside high-voltage lines whose crews need working clearance. The utility raised it before construction began. Columns were built anyway, and the State Auditor later found the project's reporting to its own board lagged what its managers knew.
Figures in USD. Every number on this page links to its source below.
The gap
Total project cost, US$ billions
The record
Pick any event. Where a control point would have sat, you'll see what ProgramWarden puts in front of a named person at that moment.
The electric utility tells the project's consultants its crews need 50 feet of working clearance around high-voltage lines along the route. In the same period the first major construction contract is awarded before environmental review is complete.
Control point · Clash detection
The utility's clearance envelope is drawn as a restricted zone with dates. The moment a guideway work zone overlaps it in space and time, an open clash exists with both parties named on it.
How the product behaves at a moment like this one. Not a claim about what would have happened on this project.
What the record shows
On the record
The utility's clearance requirement was raised in 2009 and settled by agreement in 2017, after structures had been built.
In ProgramWarden · Clash detection
Every party's ground is a zone with a date window. Overlaps between different projects are computed, counted down, and held open until someone named records how it was resolved.
On the record
The State Auditor found board reporting often contradicted the project's own internal projections.
In ProgramWarden · Named escalation
Budget variance, late gates and overdue items are computed from working records and shown the same way to every role with oversight.
On the record
The audit traced $354.4 million in change orders to contracts awarded before environmental review and federal approval.
In ProgramWarden · Evidence gates
A project that reports a phase its gates do not support is flagged as running ahead of approval, by name, on the dashboard.
None of it needed a megaproject. The same three things happen on a $20 million station upgrade, with fewer people watching.
Independent analysis of public records. ProgramWarden was not used on this project and has no relationship with, or endorsement from, any organization named. Statements about what a control "would have" shown are illustrations of how the product works, not claims about what would have happened.
Set up one program, one gate and its evidence in an afternoon. Fourteen days of the full product, no card.
The walkthrough is with the founder, an owner-side program manager. No sales deck.